UNDERPASS AT ASKARI-11 LAHORE
OVERVIEW
Askari 11 underpass is the first project for General Headquarters Pakistan Army of HCS. This underpass facilitates the traffic flow of Cantonment Lahore connecting Sector A with Sector B. Completed just in 228 days.
PROJECT STATISTICS
</p> <p> [align-left] | |
Location | Lahore |
Client | GHQ |
Ownership | GHQ |
Consultant | Pakistan Consulting Associates J-V (PCA-CEC) |
Cost | PKR 196 Million |
Start Date | October 16, 2012 |
End Date | May 31, 2013 |
</p> <p> |
PROJECT HIGHLIGHTS
</p> <p>[align-left] | |
Earthwork | 10,361 m3 |
Excavation | 50,132 m3 |
Base/Sub Base | 2,875 m3 |
Concrete | 11,570 m3 |
Asphalt | 448 m3 |
Reinforcement | 832 Ton |