MUSLIM TOWN FLYOVER LAHORE

OVERVIEW

The project involved the construction of an overpass along Ferozepur Road at the junction of Canal/Wahdat in order to make Ferozepur Road a signal-free intersection and ultimately streamline traffic coming from various parts of the city. Before the construction of the project, a traffic diversion plan was implemented to try to ensure smooth traffic, but major traffic jams still occurred. The structures consist of massive reinforced concrete piles, piers, transoms, I&L-shape prestressed girders, box girders and deck slabs. Reinforced concrete retaining walls are designed to serve as ramps of flyovers.

PROJECT STATISTICS

</p> <p> [align-left]
Project LocationLahore
ClientNational Logistics Cell (NLC)
OwnershipC & W, Government of Punjab
ConsultantNespak
Project ValuePKR 2,082 Million
Start DateOctober 28, 2011
Completion DateApril 21, 2012
Completed In A Record Time Of 177 Days
</p> <p>

PROJECT HIGHLIGHTS

</p> <p> [align-left]
Earthwork34,412 m3
Excavation30,755 m3
Base/Sub Base31,128 m3
Concrete51,515 m3
Asphalt9,130 m3
Reinforcement7,079 Ton
</p> <p>