METRO BUS ISLAMABAD (PACKAGE 1)
OVERVIEW
Metro Bus Project Islamabad was initially divided into 5 packages. Package 1 was awarded to HCS comprising flyovers, bridges and pedestrian underpasses. HCS was earliest to complete its package and declared as number one contractor by honorable Chief Minister of Punjab Mian Muhammad Shahbaz Sharif for quality work.
PROJECT STATISTICS
</p> <p> [align-left][align-left] | |
Project Location | Rawalpindi |
Client | Rawalpindi Development Authority (RDA) |
Ownership | RDA, Government of Punjab |
Consultant | Nespak |
Project Value | PKR 3,350 Million |
Start Date | April 23,2014 |
Completion Date | March 27, 2015 |
</p> <p> |
PROJECT HIGHLIGHTS
</p> <p> [align-left][align-left] | |
Earthwork | 54,230 m3 |
Excavation | 305,263 m3 |
Base/Sub Base | 31,360 m3 |
Concrete | 78,032 m3 |
Asphalt | 15,636.00 m3 |
Reinforcement | 6,658 Ton |