FLYOVER AT CHANDNI CHOWK RAWALPINDI

OVERVIEW

The construction of the Chandni Chowk Flyover was started at a busy locality of Rawalpindi, on November 5, 2011. The flyover was completed in 127 days. The length of the flyover is 403 metres, and it has three lanes each side. On an average, 128,900 vehicles pass through this junction daily and the flyover will help solve the traffic mess on Benazir Bhutto Road, particularly at Chandni Chowk, which had been a great concern for motorists, transporters and commuters.

PROJECT STATISTICS

</p> <p> [align-left]
Project LocationRawalpindi
ClientNational Logistics Cell (NLC)
OwnershipC & W, Government of Punjab
ConsultantEngineering Associates
Project ValuePKR 828 Million
Start DateNovember 05, 2011
Completion DateMarch 10, 2012
Completed In A Record Time Of 126 Days
</p> <p>

PROJECT HIGHLIGHTS

</p> <p> [align-left]
Earthwork10,825 m3
Excavation15,601 m3
Base/Sub Base6,425 m3
Concrete28,346 m3
Asphalt4,317 m3
Reinforcement3,434 Ton
</p> <p>