DUALIZATION OF LAHORE- KASUR ROAD
OVERVIEW
Dualization of Lahore- Kasur Road was a 5.18 Km road portion awarded by communication and works department to HCS. The project became a huge source of relief for the people as it was the most congested and busiest road. HCS delivered the project in 183 days with state of the art construction and ambiance.
PROJECT STATISTICS
</p> <p> [align-left][align-left] | |
Project Location | Kasur |
Client | Communication & Works |
Ownership | C & W Government of Punjab |
Consultant | Nespak |
Project Value | PKR. 755 Million |
Start Date | April 02 , 2010 |
Completion Date | October 01 , 2010 |
</p> <p> |
PROJECT HIGHLIGHTS
</p> <p>[align-left][align-left] | |
Earthwork | 250,119 m3 |
Excavation | 929 m3 |
Base/Sub | 43,444 m3 |
Concrete | 8,276 m3 |
Asphalt | 13,739 m3 |
Reinforcement | 492 Ton |
Length | 5.18 KM |