MUSLIM TOWN FLYOVER LAHORE
OVERVIEW
The project involved the construction of an overpass along Ferozepur Road at the junction of Canal/Wahdat in order to make Ferozepur Road a signal-free intersection and ultimately streamline traffic coming from various parts of the city. Before the construction of the project, a traffic diversion plan was implemented to try to ensure smooth traffic, but major traffic jams still occurred. The structures consist of massive reinforced concrete piles, piers, transoms, I&L-shape prestressed girders, box girders and deck slabs. Reinforced concrete retaining walls are designed to serve as ramps of flyovers.
PROJECT STATISTICS
%0A%0A%5Balign-left%5D,[align-left]|[align-left]Project%20Location,[align-left]Lahore|[align-left]Client,[align-left]National%20Logistics%20Cell%20(NLC)|[align-left]Ownership,[align-left]C%20%26%20W%2C%20Government%20of%20Punjab|[align-left]Consultant,[align-left]Nespak|[align-left]Project%20Value,[align-left]PKR%202%2C082%20Million|[align-left]Start%20Date,[align-left]October%2028%2C%202011|[align-left]Completion%20Date,[align-left]April%2021%2C%202012|[align-left;b;c#dd3333]Completed%20In%20A%20Record%20Time%20Of%20177%20Days,[align-left]|[align-left],[align-left]%0A%0A
[/vc_table]
PROJECT HIGHLIGHTS
%0A%0A%5Balign-left%5D,[align-left]|[align-left]Earthwork,[align-left]34%2C412%20m3|[align-left]Excavation,[align-left]30%2C755%20m3|[align-left]Base%2FSub%20Base,[align-left]31%2C128%20m3|[align-left]Concrete,[align-left]51%2C515%20m3|[align-left]Asphalt,[align-left]9%2C130%20m3|[align-left]Reinforcement,[align-left]7%2C079%20Ton|[align-left],[align-left]%0A%0A
[/vc_table]