Construction of Chaubucha Underpass renamed Beijing Underpass along Canal Road Lahore

OVERVIEW


The project involves construction of four underpasses along the Canal Bank Road, Lahore. Two of these underpasses are located on Thokar Niaz Baig bound and the other two are situated on Jallo bound. In addition, the existing Shalimar Underpasses are to be lowered to a height of 5.1 meters. The project was started on March 31,2017 and is expected to be completed on November 25,2017 incurring a total cost of PKR 3500 million

PROJECT STATISTICS

</p> <p> [align-left][align-left]
Project Location:Construction of Chaubucha Underpass along Canal Road Lahore.
ClientLahore Development Authority
OwnershipLDA Government of Punjab
Project Value3500
Start DateMarch 31, 2017 (Railway Bridge’s (July, 2017)
Completion DateNovember 25, 2017