LAHORE RING ROAD QUAID-E-AZAM INTERCHANGE (PACKAGE-10)
OVERVIEW
Work on the first Package i,e Saggian Chowk Interchange set the tone and grounds of mutual trust between employer and HCS. In time project execution with quality truly exhibits the skills, strengths and standards of HCS. Quaid e Azam interchange was one of the biggest packages of Lahore Ring Road in terms of cost and delivered just in 310 calendar days.
PROJECT STATISTICS
</p> <p> [align-left] | |
Project Location | Lahore |
Client | National Logistics Cell (NLC) |
Ownership | PMU, Government of Punjab |
Consultant | Nespak |
Project Value | PKR. 1,500 Million |
Start Date | February 25, 2009 |
Completion Date | December 31, 2009 |
Early Completion | |
</p> <p> |
PROJECT HIGHLIGHTS
</p> <p>[align-left] | |
Earthwork | 1,235,713 m3 |
Excavation | 43,450 m3 |
Base/Sub Base | 89,897 m3 |
Concrete | 22,824 m3 |
Asphalt | 21,941 m3 |
Reinforcement | 1,973 Ton |
Length | 2 KM |