HCS have completed following projects.

Project Name
Project Cost (Million Rupees)
Client
Ownership
Commencement Date
Completion Date
LAHORE RING ROAD, CONSTRUCTION OF INTERCHANGE AT SAGGIAN (PACKAGE-4) 959 NLC C&W Punjab February 3, 2009 June 30, 2009
LAHORE RING ROAD, CONSTRUCTION OF INTERCHANGE AT AIRPORT ACCESS ROAD (PACKAGE-7) 1015 NLC C&W Punjab Sep 12, 2009 June 11, 2010 (Early Completion)
LAHORE RING ROAD, CONSTRUCTION OF INTERCHANGE AT HARBANSPURA CANAL CROSSING (PACKAGE-9) 1200 NLC C&W Punjab March 01, 2009 Feb 28, 2010 (Early Completion)
LAHORE RING ROAD, CONSTRUCTION OF INTERCHANGE AT GT ROAD (PACKAGE-10) 1500 NLC C&W Punjab Feb 25, 2009 March 1st, 2010 (Early Completion)
LAHORE RING ROAD, CONSTRUCTION OF ROAD PORTION FROM MAHMOOD BOOTI TO LAKHU DAIR (PACKAGE-13) 450 NLC C&W Punjab May 30, 2009 Oct 30, 2009
DUALIZATION OF LAHORE - KASUR ROAD. GROUP-3 KM 49.82 TO KM 55.00. LENGTH 5.18 KM
KASUR CITY PORTION
755 C & W Government of Punjab April 02, 2010
Oct 01, 2010

(Substantially completed in record period of 2-1/2 Months on June 21, 2010)
DUALIZATION OF LAHORE FEROZPUR ROAD (LAHORE TO KASUR) - SECTION KM 15.15 TO KM 26.65 LENGTH 11.50 KM FROM KHAIRA DISTRIBUTORY TO KAHNA (PHASE - 1)
220
C & W
Government of Punjab
June 25, 2010

Sep 24, 2010

Substantially completed on August 30, 2010


HCS is working on following current projects.

Project Name
Project Cost (Million Rupees)
Client
Commencement Date
Completion Date
Status
Completed as on August 31, 2010

LAHORE RING ROAD, CONSTRUCTION OF INTERCHANGE AT GHAZI ROAD, (PACKAGE-11) (Subcontracted Works from NLC up to WBM level and Structures)
1000
NLC
Feb 15, 2010
Sep 30, 2010
45 %
NEW BENAZIR BHUTTO INTERNATIONAL AIRPORT ISLAMABAD

PACKAGE 1, AIRSIDE INFRASTRUCTURE (CIVIL WORKS)

(A JOINT VENTURE OF LAGAN CONSTRUCTION, TECHNICAL ASSOCIATE AND HABIB CONSTRUCTION SERVICES PVT. LTD.)
10924
CAA
Feb 15, 2010
July 02, 2011
35.73 %
IMPROVEMENT OF ROAD FROM LAHROE BRANCH CANAL FROM THOKAR NIAZ BAIG TO DEFENCE ROAD INCLUDING ADDITION OF 3RD LANE. LENGTH 10.96 KM IN DISTRICT LAHORE
315
C & W Govt of Punjab
May 24, 2010
Sep 23, 2010
40 %

(Work slow down on directions of the Employer)

GHABBIR DAM PROJECT, SMALL DAM PROJECT ON EPC BASIS NEAR CHAKWAL

(A JOINT VENTURE OF DONGFANG TECHNICAL ASSOCIATE AND HABIB CONSTRUCTION SERVICES PVT. LTD.)

6848
WAPDA
Declared lowest bidder in bid opening dated May 17, 2010 at WAPDA House, Lahore
--
--
NEW BENAZIR BHUTTO INTERNATIONAL AIRPORT ISLAMABAD, LANDSIDE INFRASTRUCTURE (PACKAGE-8A)

(A JOINT VENTURE OF LAGAN CONSTRUCTION, TECHNICAL ASSOCIATE AND HABIB CONSTRUCTION SERVICES PVT. LTD.)
6852
CAA
Acceptance Letter has been received from the Employer dated July 15, 2010
--
--
CONSTRUCTION OF SIALKOT AIRPORT EXTENSION OF APRON
194
SIAL
Declared lowest bidder in bid opening dated June 24, 2010
--
--