Current Projects

List View

Serial NoProject Name Project Cost (Million Rupees) ClientOwnership ConsultantsCommencement Date Completion DateStatus Completed as on
November 30, 2016
1Construction of Metro Bus System Multan Package-5 Vehari Road to Khumaharan Chowk Length=5.584Km
3756Multan Development AuthorityMDA Government of PunjabOsmani & CompanyMay
9, 2015
September
30 , 2016
99%
2Lahore Orange Line Metro Train Project Package-1 Construction of Civil and Allied Works from Dera Gujjran to Chauburji 13.6 KM21409Lahore Development AuthorityMetro Bus Authority Government of PunjabNESPAK-CEC JVOctober
25, 2015
Extension applied up to April 24, 201774% of available 76%
3Construction of Access Road LDA City from Ferozepur Road to Kahna Kacha Road Lahore
1089Lahore Development AuthorityLahore Development AuthorityNespakFebruary
2, 2016
December
31, 2016
94%
4Construction of Road From Thalian on M-2 to New Islamabad International Airport Including periphery Roads1921National Highway Authority NHA Ministry of Communications Government of Pakistan M/s Asif Ali Associates LahoreApril
24, 2016
March
31, 2017
54%