LAHORE RING ROAD SAGGIAN INTERCHANGE (PACKAGE-4)

OVERVIEW

Saggian interchange includes a 1.08 – kilometer – long (0.67 mi) portion of the main Lahore Ring Road, a 2.12-kilometre (1.32 mi) outfall road, a flyover, two subways and two utility culverts. The project also includes landscaping, development of service areas and bus-bays.

PROJECT STATISTICS

</p> <p> [align-left][align-left]
Project Location:Lahore
ClientNational Logistics Cell (NLC)
OwnershipPMU, Government of Punjab
ConsultantNespak
Project ValuePKR. 959 Million
Start DateFebruary 03, 2009
Completion DateMay 01, 2009
</p> <p>

PROJECT HIGHLIGHTS

</p> <p>[align-left][align-left]
Earthwork1,669,107 m3
Excavation158,273 m3
Base/Sub Base72,591 m3
Concrete21,645 m3
Asphalt18,113 m3
Reinforcement2,109 Ton
Length1KM